Accounting Software Project

Project Dashboard (2002-03-05)
Task
Resources
Trend
Journal
Icon Alpha Test
ID: AcSo.test.alpha
  • Peter Murphy
  • Sébastien Bono
Icon Up

Contract with Peter not yet signed

Reported on 2002-03-01 by Paul Henry Bullock

The paperwork is stuck with HR and I can't hunt it down.

If we don't get the contract closed within the next week, the start of the testing is at risk.

Icon Manual
ID: AcSo.manual
  • Dim Sung
  • Klaus Müller
Icon Flat

User manual completed

Reported on 2002-02-28 by Paul Henry Bullock

The doc writers did a really great job to finish on time.


Already completed tasks
WBS
Name
Start
End
Effort
Alert
Status
1
Icon Accounting Software
ID: AcSo
2002-01-20
2002-04-26
185.0
Icon Red
in progress
1.5
Icon Milestones
ID: AcSo.deliveries
2002-01-20
2002-04-26
0.0
Icon Green
in progress
1.5.1
Icon Project start
ID: AcSo.deliveries.start
2002-01-20
2002-01-20
0.0
Icon Green
done
1.1
Icon Specification
ID: AcSo.spec
2002-01-21
2002-01-29
20.0
Icon Green
done
1.4
Icon Manual
ID: AcSo.manual
2002-01-21
2002-03-01
50.0
Icon Green

Manual (ID: AcSo.manual)

User manual completed

Reported on 2002-02-28 by Paul Henry Bullock

The doc writers did a really great job to finish on time.

done
1.2
Icon Software Development
ID: AcSo.software
2002-01-29
2002-04-08
90.0
Icon Yellow
in progress
1.2.1
Icon Database coupling
ID: AcSo.software.database
2002-01-29
2002-02-12
20.0
Icon Yellow

Database coupling (ID: AcSo.software.database)

Problems with the SQL Libary

Reported on 2002-02-03 by Paul Smith

We ran into some compatibility problems with the SQL Library.

We have already contacted the vendor and are now waiting for their advise.

done

Ongoing tasks
WBS
Name
Start
End
Effort
Alert
Status
1
Icon Accounting Software
ID: AcSo
2002-01-20
2002-04-26
185.0
Icon Red
in progress
1.5
Icon Milestones
ID: AcSo.deliveries
2002-01-20
2002-04-26
0.0
Icon Green
in progress
1.2
Icon Software Development
ID: AcSo.software
2002-01-29
2002-04-08
90.0
Icon Yellow
in progress
1.2.3
Icon Back-End Functions
ID: AcSo.software.backend
2002-02-12
2002-03-05
30.0
Icon Green
in progress

Future tasks
WBS
Name
Start
End
Effort
Alert
Status
1
Icon Accounting Software
ID: AcSo
2002-01-20
2002-04-26
185.0
Icon Red
in progress
1.5
Icon Milestones
ID: AcSo.deliveries
2002-01-20
2002-04-26
0.0
Icon Green
in progress
1.5.2
Icon Technology Preview
ID: AcSo.deliveries.prev
2002-03-05
2002-03-05
0.0
Icon Green
not reached
1.5.3
Icon Beta version
ID: AcSo.deliveries.beta
2002-04-11
2002-04-11
0.0
Icon Green
not reached
1.5.4
Icon Ship Product to Customer
ID: AcSo.deliveries.done
2002-04-26
2002-04-26
0.0
Icon Green
not reached
1.2
Icon Software Development
ID: AcSo.software
2002-01-29
2002-04-08
90.0
Icon Yellow
in progress
1.2.2
Icon Graphical User Interface
ID: AcSo.software.gui
2002-03-05
2002-04-08
40.0
Icon Green
not started
1.3
Icon Software testing
ID: AcSo.test
2002-04-08
2002-04-26
25.0
Icon Red
not started
1.3.1
Icon Alpha Test
ID: AcSo.test.alpha
2002-04-08
2002-04-11
5.0
Icon Red

Alpha Test (ID: AcSo.test.alpha)

Contract with Peter not yet signed

Reported on 2002-03-01 by Paul Henry Bullock

The paperwork is stuck with HR and I can't hunt it down.

If we don't get the contract closed within the next week, the start of the testing is at risk.

not started
1.3.2
Icon Beta Test
ID: AcSo.test.beta
2002-04-11
2002-04-26
20.0
Icon Green
not started