Keyword workinghours (shift)

Purpose

Set the working hours for the shift. The working hours specification limits the availability of resources or the activity on a task to certain time slots of week days.

The shift working hours will replace the default or resource working hours for the specified time frame when assigning the shift to a resource.

In case the shift is used for a task, resources are only assigned during the working hours of this shift and during the working hours of the allocated resource. Allocations only happen when both the task shift and the resource work hours allow work to happen.

Syntax workinghours <weekday> [- <end weekday>] [, <weekday> [- <end weekday>]...] (off | <TIME> - <TIME> [, <TIME> - <TIME>...])
Arguments weekday
Weekday (sun - sat)
end weekday
Weekday (sun - sat). It is included in the interval.
Context shift
See also workinghours (project), workinghours (resource)