| The TaskJuggler Manual | ||
|---|---|---|
| Prev | Chapter 7. Property Reference | Next |
percent>complete
<percent>
| |||
|---|---|---|---|
| Description | Specifies what percentage of the task is already completed. This can be useful for project tracking. Reports with calendar elements may show the completed part of the task in a different color. The completion percentage has no impact on the scheduler. It's meant for documentation purposes only. Tasks may not have subtasks if this attribute is used. | ||
| Attributes | Name | Type | Description |
percent | INTEGER | The value must be between 0 and 100. | |
| Context | task, | ||
| Inheritable | No | Scenario Spec. | Yes |
| See also | booking | ||
project simple "Some task" "1.0" 2005-06-06 - 2005-06-26 {
now 2005-06-15
}
resource tux "Tux"
task t "Task" {
start 2005-06-06
effort 10d
allocate tux
# This task should have be be completed much more on Jun 15, but
# it's only 20% done.
complete 20
}