| milestone | |||
|---|---|---|---|
| Description | Turns the task into a special task that has no duration. You may not specify a duration, length, effort or subtasks for a milestone task. A task that only has a start or an end specification and no duration specification or sub tasks, will be recognized as milestone automatically. | ||
| Context | task, | ||
| Inheritable | No | Scenario Spec. | No |
project prj "Milestone demo" "1.0" 2005-07-15 - 2005-08-01
task project_start "Project Start" {
start 2005-07-15
milestone
}
task deadline "Important Deadline" {
start 2005-07-20
# A task with only a start or end date and no duration specification
# is automatically assumed to be a milestone.
}