interval>vacation
<interval>
| |||
|---|---|---|---|
| Description | Specify a vacation period for the resource. It can also be used to block out the time before a resource joint or after it left. For employees changing their work schedule from full-time to part-time, or vice versa, please refer to the 'Shift' property. | ||
| Attributes | Name | Type | Description |
interval | DATEINTERVAL | ||
| Context | resource, | ||
| Inheritable | Yes | Scenario Spec. | No |
| See also | vacation, shift | ||
project prj "Vacation Examples" "1.0" 2005-07-22 - 2006-01-01
# Labor Day
vacation "Labor Day" 2005-09-05
# 2 days Christmas break (27th not included!)
vacation "Christmas" 2005-12-25 - 2005-12-27
resource team "A team" {
# 2 days of team vacation
vacation 2005-10-07 +2d
resource tux2 "Tux2"
resource tux3 "Tux3" {
# And one extra day
vacation 2005-08-10
}
}
# The vacation property is also usefull when new employees start
# working in the course of a project or if someone quits.
resource tuxia "Tuxia" {
# Tuxia is a new employee as of August 1st 2005
vacation 1971-01-01 - 2005-08-01
}
resource tuxus "Tuxus" {
# Tuxus quits his job on September 1st 2005
vacation 2005-09-01 - 2030-01-01
}
task t "An important date" {
start 2005-07-22
}