dailymax <value> <unit>

dailymax <value> <unit>
Description

Sets the daily limit of a resource usage or a resource allocation to a task.

AttributesNameTypeDescription
valueREAL 
unitUNIT 
Contextlimits,
InheritableYesScenario Spec.No
See alsomonthlymax, weeklymax, yearlymax, projectmax

project limits "Limits" "1.0" 2004-03-01 - 2004-05-01

# Default limit that affects all subsequently defined resources
limits {
  weeklymax 4d
}

resource r1 "R1" { 
  # Limit the usage of this resource to a maximum of 2 hours per day,
  # 6 hours per week and 2.5 days per month.
  limits { dailymax 2h weeklymax 6h monthlymax 2.5d yearlymax 217d }
}

resource r2 "R2"

task t1 "Task 1" {
  start 2004-03-01
  duration 60d
  # allocation is subject to resource limits
  allocate r1
}

task t2 "Task 2" {
  start 2004-03-01
  duration 60d
  # limits can also be specified per allocation
  allocate r2 {
    limits { dailymax 4h weeklymax 3d monthlymax 2w projectmax 20d }
  }
}