The TaskJuggler Manual | ||
---|---|---|
Prev | Chapter 7. Property Reference | Next |
value
>
<unit
>duration
<value >
<unit >
| |||
---|---|---|---|
Description | Specifies the time the task occupies the resources. This is calendar time, not working time. 7d means one week. If resources are specified they are allocated when available. Availability of resources has no impact on the duration of the task. It will always be the specified duration. Tasks may not have subtasks if this attribute is used. | ||
Attributes | Name | Type | Description |
value | REAL | ||
unit | UNIT | ||
Context | task, | ||
Inheritable | No | Scenario Spec. | Yes |
See also | effort, length |
project duration "Duration Example" "1.0" 2005-06-06 - 2005-06-26 resource tux "Tux" task t "Enclosing" { start 2005-06-06 task durationTask "Duration Task" { # This task is 10 calendar days long. duration 10d } task intervalTask "Interval Task" { # This task is similar to the durationTask. Instead of a start # date and a duration it has a fixed start and end date. end 2005-06-17 } task lengthTask "Length Task" { # This task 10 working days long. So about 12 calendar days. length 10d } task effortTask "Effort Task" { effort 10d allocate tux } }