end <date>

end <date>
Description

The end date of the task. When specified for the top-level (default) scenario this attributes also implicitly sets the scheduling policy of the tasks to alap.

AttributesNameTypeDescription
dateDATE 
Contexttask,
InheritableYesScenario Spec.Yes
See alsoperiod, start, maxend, minend, scheduling, endbuffer

project duration "Duration Example" "1.0" 2005-06-06 - 2005-06-26

resource tux "Tux"

task t "Enclosing" {
  start 2005-06-06
  task durationTask "Duration Task" {
    # This task is 10 calendar days long.
    duration 10d
  }

  task intervalTask "Interval Task" {
    # This task is similar to the durationTask. Instead of a start
    # date and a duration it has a fixed start and end date.
    end 2005-06-17
  }

  task lengthTask "Length Task" {
    # This task 10 working days long. So about 12 calendar days.
    length 10d
  }

  task effortTask "Effort Task" {
    effort 10d
    allocate tux
  }
}