project duration "Duration Example" "1.0" 2005-06-06 - 2005-06-26
resource tux "Tux"
task t "Enclosing" {
start 2005-06-06
task durationTask "Duration Task" {
# This task is 10 calendar days long.
duration 10d
}
task intervalTask "Interval Task" {
# This task is similar to the durationTask. Instead of a start
# date and a duration it has a fixed start and end date.
end 2005-06-17
}
task lengthTask "Length Task" {
# This task 10 working days long. So about 12 calendar days.
length 10d
}
task effortTask "Effort Task" {
effort 10d
allocate tux
}
}