overtime 0: | You can only book available working hours. (Default) |
overtime 1: | You can book off-hours as well. |
overtime 2: | You can book normal working hours, off-hours and vacations. |
project prj "Project" "1.0" 2003-06-05 +1m {
# The baseline date for the projection.
now 2003-06-15
scenario plan "Plan" {
# Compute when the task will be ready based on the already done
# work and the current date.
projection { strict }
}
}
resource r1 "Resource 1"
task t1 "Task 1" {
start 2003-06-05
effort 10d
allocate r1
}
supplement resource r1 {
# This is the work that has been done up until now by r1.
booking t1 2003-06-06 +8h { sloppy 2 }
booking t1 2003-06-08 +4h,
2003-06-09 +4h { sloppy 2 }
# Book interval that extends into off-hours.
booking t1 2003-06-11-8:00 +10h { overtime 1 }
}