project prj "Project" "1.0" 2005-01-01 - 2005-03-01
resource r "Resource"
task t "Task" {
task s "SubTask" {
start 2005-01-01
effort 5d
allocate r
}
}
# Just a very basic report with some standard columns
htmltaskreport "SimpleReport.html" {
columns hierarchindex, name, start, end, weekly
}
# Report with custom colum title
htmltaskreport "CustomTitle.html" {
columns hierarchindex, name { title "Work Item" }, effort
}
# Report with custom colum title and subtitle
htmltaskreport "CustomSubTitle.html" {
columns hierarchindex, name,
monthly { title " " subtitle "$${month} $${year}" }
loadunit days
}
# Report with efforts only for leaf tasks
htmltaskreport "LeafEfforts.html" {
columns hierarchindex, name,
effort { hidecelltext ~isLeaf() }
}
# Report with link in title of calendar
htmltaskreport "LinkURL.html" {
columns hierarchindex, name,
monthly { subtitleurl "Monthly-Detail-$${month}.html" }
}
# Report with link to page with furter task details
htmltaskreport "LinkToTaskDetails.html" {
columns hierarchindex,
name { cellurl "TaskDetails-$${taskid}.html"
hidecellurl ~isLeaf() }, start, end
}
# Report with index and task name combined in one single column
htmltaskreport "CombinedColumn.html" {
columns name { celltext "$${hierarchno} $${0}"}, start, end, weekly
}