project simple "Simple Project" "1.0" 2005-06-06 - 2005-06-26
resource tux "Tux"
resource tuxia "Tuxia"
task items "Project breakdown" {
start 2005-06-06
task plan "Plan work" {
task phase1 "Phase 1" {
effort 5d
allocate tuxia
}
task phase2 "Phase 2" {
effort 2d
allocate tux
}
}
task implementation "Implement work" {
effort 5d
allocate tux
depends !plan
}
task acceptance "Customer acceptance" {
duration 5d
depends !implementation
}
}
taskreport "Project Breakdown" {
columns start, end, effort
# Open only the first level of tasks
rolluptask treelevel() > 1
}
resourcereport "Resource Allocations" {
columns id, effort
# We only want to see the tasks with real work (without parents),
# sorted by name
sorttasks nameup
hidetask ~isleaf()
}