The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< dailymin << Table Of Contents >> date >>


Keyword dailyworkinghours

Purpose
Set the average number of working hours per day. This is used as the base to convert working hours into working days. This affects for example the length task attribute. The default value is 8 hours and should work for most Western countries. The value you specify should match the settings you specified as your default working hours.
Syntax dailyworkinghours <hours>
Arguments hours
Average number of working hours per working day
Context project

project prj "Example Project" "1.0" 2007-01-01 - 2007-03-09 {
  # The following attributes are all optional. They illustrate the
  # default values. These attributes are only needed if you want to
  # specify different values than those listed below.
  timingresolution 60min
  timezone "America/Denver"
  dailyworkinghours 8
  yearlyworkingdays 260.714
  timeformat "%Y-%m-%d %H:%M"
  shorttimeformat "%H:%M"
  currencyformat "(" ")" "," "." 0
  weekstartsmonday
  workinghours mon - fri 9:00 - 12:00, 13:00 - 18:00
  workinghours sat, sun off
  scenario plan "Plan" {
  }
}

task t "Task" {
  start 2007-01-01
}