The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< listtype (column) << Table Of Contents >> logicalexpression >>


Keyword loadunit

Purpose
Determines what unit should be used to display all load values in this report.
Syntax loadunit (days | hours | longauto | minutes | months | quarters | shortauto | weeks | years)
Arguments days
Display all load and duration values as days.
hours
Display all load and duration values as hours.
longauto
Automatically select the unit that produces the shortest and most readable value. The unit name will not be abbreviated. It will not use quarters since it is not common.
minutes
Display all load and duration values as minutes.
months
Display all load and duration values as months.
quarters
Display all load and duration values as quarters.
shortauto
Automatically select the unit that produces the shortest and most readable value. The unit name will be abbreviated. It will not use quarters since it is not common.
weeks
Display all load and duration values as weeks.
years
Display all load and duration values as years.
Context export, resourcereport, taskreport, textreport, tracereport, accountreport



<< listtype (column) << Table Of Contents >> logicalexpression >>


Copyright (c) 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 by Chris Schlaeger <cs@taskjuggler.org>.TaskJuggler is a trademark of Chris Schlaeger.