Purpose
Normally, columns with calculated values take the specified report period into account when calculating their values. With this attribute, the user can specify a start date for the period that should be used when calculating the values of this column. It does not have an impact on columns with time invariant values.
Syntax start <date>
Arguments date
See date for details.