The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< treelevel << Table Of Contents >> vacation (resource) >>


Keyword vacation

Purpose
Specify a global vacation period for all subsequently defined resources. A vacation can also be used to block out the time before a resource joined or after it left. For employees changing their work schedule from full-time to part-time, or vice versa, please refer to the 'Shift' property.
Syntax vacation <name> <interval3> [, <interval3>...]
Arguments name
Name or purpose of the vacation
interval3
See interval3 for details.
Context properties



<< treelevel << Table Of Contents >> vacation (resource) >>