The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< workinghours (project) << Table Of Contents >> workinghours (shift) >>


Keyword workinghours (resource)

Purpose
Set the working hours for a specific resource. The working hours specification limits the availability of resources to certain time slots of week days.
Syntax workinghours <weekday> [- <end weekday>] [, <weekday> [- <end weekday>]...] (off | <TIME> - <TIME> [, <TIME> - <TIME>...])
Arguments weekday
Weekday (sun - sat)
end weekday
Weekday (sun - sat). It is included in the interval.
Context resource, supplement (resource)
See also workinghours (project), workinghours (shift)



<< workinghours (project) << Table Of Contents >> workinghours (shift) >>


Copyright (c) 2006 - 2025 by Chris Schlaeger <cs@taskjuggler.org>.TaskJuggler is a trademark of Chris Schlaeger.