| Description | Specifies the minimum required gap between the end of a preceding task and the start of this task, or the start of a following task and the end of this task. This is working time, not calendar time. 7d means 7 working days, not one week. Whether a day is considered a working day or not depends on the defined working hours and global vacations. | ||
| Attributes | Name | Type | Description |
value | REAL | ||
unit | UNIT | ||
| Context | depends, precedes, | ||
| Inheritable | Yes | Scenario Spec. | Yes |
| See also | gapduration, length | ||
project prj "Example Project" "1.0" 2005-05-29 - 2005-07-01
task t1 "Task 1" {
start 2005-05-29
}
task t2 "Task 2" {
# starts 5 calendar days after t1
depends !t1 { gapduration 5d }
}
task t3 "Task 3" {
# starts 5 working days after t1
depends !t1 { gaplength 5d }
}