weekday>
[, <weekday> ... ]
<interval>
[, <interval> ... ]workinghours
<weekday>
[, <weekday> ... ]
<interval>
[, <interval> ... ]
| |||
|---|---|---|---|
| Description | The working hours specification limits the availability of resources to certain time slots of week days. | ||
| Attributes | Name | Type | Description |
weekday | WEEKDAY | ||
interval | TIMEINTERVAL | ||
| Context | project, resource, shift, | ||
| Inheritable | Yes | Scenario Spec. | No |
| See also | dailyworkinghours, yearlyworkingdays | ||
project prj "Example Project" "1.0" 2000-01-01 - 2000-03-09 {
# The following attributes are all optional. They illustrate the
# default values. These attributes are only needed if you want to
# specify different values than those listed below.
dailyworkinghours 8
yearlyworkingdays 260.714
timingresolution 60min
timeformat "%Y-%m-%d %H:%M"
shorttimeformat "%H:%M"
currencyformat "(" ")" "," "." 0
weekstartsmonday
workinghours mon - fri 9:00 - 12:00, 13:00 - 18:00
workinghours sat, sun off
scenario plan "Plan" {
}
}
task t "Task" {
start 2000-01-01
}