| limits | |||
|---|---|---|---|
| Description | Specifies limits on the usage of a resource in general, or of the allocation of a resource to a task. This property replaces the less flexible properties maxeffort and load. When applied to an allocation this limits the use of all alternative resources or group members as a whole. There has been a bug in version 2.0.x that resulted in faulty limit computation. This has been fixed with version 2.1. | ||
| Optional Attributes | dailymax, weeklymax, monthlymax, yearlymax, projectmax | ||
| Context | The TJP File, allocate, resource, | ||
| Inheritable | Yes | Scenario Spec. | No |
project limits "Limits" "1.0" 2004-03-01 - 2004-05-01
# Default limit that affects all subsequently defined resources
limits {
weeklymax 4d
}
resource r1 "R1" {
# Limit the usage of this resource to a maximum of 2 hours per day,
# 6 hours per week and 2.5 days per month.
limits { dailymax 2h weeklymax 6h monthlymax 2.5d yearlymax 217d }
}
resource r2 "R2"
task t1 "Task 1" {
start 2004-03-01
duration 60d
# allocation is subject to resource limits
allocate r1
}
task t2 "Task 2" {
start 2004-03-01
duration 60d
# limits can also be specified per allocation
allocate r2 {
limits { dailymax 4h weeklymax 3d monthlymax 2w projectmax 20d }
}
}