factor>load
<factor>
| |||
|---|---|---|---|
| Description | This property has been replaced by limits. The further usage of load is strongly discouraged. It will be dropped from future versions of TaskJuggler. Specifies the daily load of a resource for an allocation. A load of 1.0 (default) means the resource is allocated for as many hours as specified by dailyworkinghours. A load of 0.5 means half that many hours. This only works if enough working hours have been specified for the particular day. | ||
| Attributes | Name | Type | Description |
factor | REAL | ||
| Context | |||
| Inheritable | No | Scenario Spec. | No |
| See also | workinghours, vacation | ||