project prj "Example" "1.0" 2000-01-01 - 2000-03-31
shift s1 "Shift1" {
# Special working hours Monday to Wednesday. Use program defaults
# for other days.
workinghours mon 10:00 - 12:00, 13:00-15:00
workinghours tue 9:00-14:00
workinghours wed off
shift s2 "Shift2" {
# Like s1 but with different times on Monday
workinghours mon 10:00 - 17:00
}
}
resource r1 "Resource1" {
shift s1 2000-01-01 - 2000-01-10
shift s2 2000-01-11 - 2000-01-20
}
shift s3 "Part-time schedule 1" {
# The resource works on mondays, wednesdays and fridays.
# The days that the resource doesn't work must be mentioned
# explicitely otherwise the defaults values are used (usually
# full-time employment).
workinghours mon,fri 9:00 - 12:00, 13:00-18:00
workinghours wed 9:00 - 12:00
workinghours tue, thu off
}
shift s4 "Part-time schedule 2" {
# The resource changes his schedule to work on tuesday and
# thursdays. The days that the resource doesn't work must be
# mentioned explicitely, otherwise the default values are used
# (usually full-time employment).
workinghours tue, thu 9:00 - 12:00, 13:00-18:00
workinghours mon, wed, fri off
}
# Now determine when these schedules are applicable
resource r2 "Resource2" {
# r2 works three days a week from January to June
shift s3 2005-01-01 - 2005-01-15
# r2 switches to two days a week
shift s4 2005-01-15 - 2006-01-01
}
task t1 "Task1" {
start 2000-01-01
length 200h
# During the specified interval only work at the shift s2 working
# hours.
shift s2 2000-01-09 - 2000-01-17
}