workinghours <weekday> [, <weekday> ... ] <interval> [, <interval> ... ]

workinghours <weekday> [, <weekday> ... ] <interval> [, <interval> ... ]
Description

The working hours specification limits the availability of resources to certain time slots of week days.

AttributesNameTypeDescription
weekdayWEEKDAY 
intervalTIMEINTERVAL 
Contextproject, resource, shift,
InheritableYesScenario Spec.No
See alsodailyworkinghours, yearlyworkingdays

project prj "Example Project" "1.0" 2000-01-01 - 2000-03-09 {
  # The following attributes are all optional. They illustrate the
  # default values. These attributes are only needed if you want to
  # specify different values than those listed below. 
  dailyworkinghours 8
  yearlyworkingdays 260.714
  timingresolution 60min
  timeformat "%Y-%m-%d %H:%M"
  shorttimeformat "%H:%M"
  currencyformat "(" ")" "," "." 0
  weekstartsmonday
    workinghours mon - fri 9:00 - 12:00, 13:00 - 18:00
    workinghours sat, sun off
  scenario plan "Plan" {
  }
}

task t "Task" {
  start 2000-01-01
}