Keyword mandatory

Purpose
Makes a resource allocation mandatory. This means, that for each time slot only then resources are allocated when all mandatory resources are available. So either all mandatory resources can be allocated for the time slot, or no resource will be allocated.
Syntax mandatory
Arguments none
Context allocate