Keyword markdate

Purpose
Specify the reference date that TaskJuggler uses as date that can be specified and set by the user. It can be used as additional point in time to help with tracking tasks. If no value is specified, the current value of the system clock is used.
Syntax markdate <date>
Arguments date
Alternative date to be used as custom date specified by the user
Context project