The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< shift << Table Of Contents >> shift (resource) >>


Keyword shift (allocate)

This keyword should no longer be used. It will be removed in future versions of this software.

Use shifts (allocate) instead.

Purpose
Limits the allocations of resources during the specified interval to the specified shift. Multiple shifts can be defined, but shift intervals may not overlap. Allocation shifts are an additional restriction to the task shifts and resource shifts or resource working hours. Allocations will only be made for time slots that are specified as duty time in all relevant shifts. The restriction to the shift is only active during the specified time interval. Outside of this interval, no restrictions apply.
Syntax shift <shift> [<interval2>]
Arguments shift [ID]
The ID of a defined shift
interval2
See interval2 for details.
Context allocate
See also shifts (allocate)