Keyword timesheetreport

Purpose
For projects that flow mostly according to plan, TaskJuggler already knows much of the information that should be contained in the time sheets. With this property, you can generate a report that contains drafts of the time sheets for one or more resources. The time sheet drafts will be for the specified report period and the specified trackingscenario.
Syntax timesheetreport [<id>] <file name> [{ <attributes> }]
Arguments id [ID]
An optional ID. If you ever want to reference this property, you must specify your own unique ID. If no ID is specified, one will be automatically generated. These IDs may become visible in reports, but may change at any time. You may never rely on automatically generated IDs.
file name [STRING]
The name of the time sheet report file to generate. It must end with a .tji extension, or use . to use the standard output channel.
Context properties

Attributes Name Scen. spec. Inh. fm. Global Inh. fm. Parent
end (report) x x
hideresource
hidetask
period (report)
sortresources
sorttasks
start (report) x x