The TaskJuggler User Manual

Project Management beyond Gantt Chart Drawing


<< maximum << Table Of Contents >> milestone >>


Keyword maxstart

Purpose
Specifies the maximum wanted start time of the task. The value is not used during scheduling, but is checked after all tasks have been scheduled. If the start of the task is later than the specified value, then an error is reported.
Syntax maxstart <date>
Arguments date
See date for details.
Context task, supplement (task)



<< maximum << Table Of Contents >> milestone >>


Copyright (c) 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 by Chris Schlaeger <cs@taskjuggler.org>.TaskJuggler is a trademark of Chris Schlaeger.