Keyword milestone

Purpose

Turns the task into a special task that has no duration. You may not specify a duration, length, effort or subtask for a milestone task.

A task that only has a start or an end specification and no duration specification, inherited start or end dates, no dependencies or sub tasks, will be recognized as milestone automatically.

Syntax milestone
Arguments none
Context task, supplement (task)