Keyword | milestone |
Purpose | Turns the task into a special task that has no duration. You may not specify a duration, length, effort or subtask for a milestone task. A task that only has a start or an end specification and no duration specification, inherited start or end dates, no dependencies or sub tasks, will be recognized as milestone automatically. |
|
Syntax | milestone |
|
Arguments | none | |
Context | task, supplement (task) |