<< effort << | Table Of Contents | >> effortleft >> |
Keyword | effortdone |
Purpose | Specifies how much effort of the task has already been completed. This can only be used for effort based tasks and only if the task is scheduled in projection mode. No bookings must be specified for the scenario. TaskJuggler is unable to create exact bookings for the time period before the current date. All effort values prior to the current date will be reported as zero. This attribute forces the task to be scheduled in ASAP mode. The task must have a predetermined start date. |
|
Syntax | effortdone <value> (min | h | d | w | m | y) |
|
Arguments | value | A floating point or integer number |
min | minutes |
|
h | hours |
|
d | days |
|
w | weeks |
|
m | months |
|
y | years |
|
Context | task, supplement (task) | |
See also | effort, effortleft, schedulingmode, trackingscenario |
<< effort << | Table Of Contents | >> effortleft >> |